Task - Add a status field
Submitted by Biboobox on Wed, 08/27/2008 - 08:09.
| Project: | ProjectPier |
| Version: | 0.8.0.3 |
| Component: | Code |
| Category: | feature request |
| Priority: | normal |
| Assigned: | Unassigned |
| Status: | closed - by design |
Jump to:
Description
Currently, when a task is completed, there is no way to indicate its status. The only solution i found is to delete the task.
It would be very useful to have a task_status field with basically two values ('Open', 'Closed'). By default, only open tasks are displayed and a new link in the tasks tab allows the user to see the closed ones.

Hi Biboobox,
I'm confused... can't you check the task as done?
See this screenshot:
http://projectpier.org/dashboard-my-tasks
Can you please confirm what you mean exactly? Otherwise I will close this issue since an open/closed status already exists.
Thanks!
Yes, sorry, you can consider it as closed, i did not understood the open/completed system up to now. So everything is OK on that side, sorry for my misunderstanding!
No worries Biboobox. Glad I could clear that up for you! :)