Milestone "Days Left" Mis-calculated.

Project:ProjectPier
Version:0.8.5.0-Beta1
Component:User interface
Category:bug report
Priority:normal
Assigned:Unassigned
Status:new
Description

If a Milestone is for Friday May 7th. The alert on Wednesday May 5th says there is 1 day left, instead of 2.

#1
Priority:critical» normal

I see that this is probably working as designed. The day begins at 12:01 am. Milestones are usually calculated as EOD (end of day), not 12:01 on the day.