Road Map: 0.8.5

Goals

This release will concentrate on adding features to project and fixing code to be more secure. Also changes in preparation for refactoring the framework in 0.9.0

Milestones / Timeline

Planned stages for release of version 0.8.5 of ProjectPier.

Date Stage Description
Feb 1, 2008 Code Freeze Description
Feb 14 - March 15, 2008 Betas Description
March 15 - April 15, 2008 Release Candidates Description
April 1, 2008 String Freeze No new changes to the interface strings so that the translators can start working on updating the available translations
May, 2008 Final Release Description